From deposit to arrival: the full timeline

From enquiry to commissioning: what actually takes the time

Buyers ask “how long is the lead time” and expect one number. The honest answer is that the machine is rarely the slow part. Booking, sailing and customs usually take longer than building a standard model.

Here is the full sequence, with the stages that commonly add weeks.

The sequence

Stage What happens What delays it
1. Enquiry Material, output, site, destination Vague material description — the single biggest cause of a wrong proposal
2. Selection Model and configuration proposed Waiting for the buyer to compare options
3. Quotation Line-item pricing, scope, terms Missing destination port, or unclear packing requirement
4. Deposit Production scheduled Bank transfer time, internal approvals
5. Production Machine built to order Non-standard options, coating, special voltage
6. Inspection Photographs, video, measurements Balance payment rounds
7. Balance Paid on approved report Bank delay, or a query on the report
8. Booking Container or flat rack space Vessel space at peak season — often the longest wait
9. Loading Lashing, photographs, seal Weather, port congestion
10. Voyage Sailing to destination Route, transhipment
11. Customs Clearance at destination Missing or inconsistent documents
12. Commissioning Installation, first run Foundation work, power supply readiness

The stages that surprise buyers

Booking is not instant

Container and flat-rack space is booked weeks ahead. In peak season a machine that is finished and inspected can still wait for a vessel. This is outside any supplier’s control, and it is why the shipping date should be treated as an estimate until the booking is confirmed.

Customs is a document problem, not a machine problem

Almost every clearance delay comes from a document: an HS code that does not match the description, a missing certificate of origin, a commercial invoice value that does not match the payment record. The machine is fine; the paperwork is not.

Commissioning waits for the site

The machine arrives, and the foundation is not poured, or the power supply is not connected, or the crane is not ready. A machine sitting on a truck for three weeks is not a supplier problem — but it is the most common reason commissioning slips.

What you can do to shorten it

  1. Describe the material precisely in the first message: what it is, maximum dimensions, how it arrives, what you want out of it.
  2. Name the destination port and the trade term you want.
  3. Prepare the site while the machine is in production, not while it is on the water.
  4. Confirm the HS code with your broker early — before the invoice is issued, not after.
  5. Book space as early as the supplier allows; do not wait for the balance payment to talk about shipping.

Frequently asked questions

How long does a standard machine take?

Seven days for standard models. Magnets, hydraulic grabs and double-cylinder shears are confirmed per model, because they are built against the carrier specification.

What is the total time from deposit to arrival?

Production plus inspection plus booking plus sailing plus clearance. The voyage is the largest single block and depends entirely on your destination — ask for it against your port, not as a general figure.

Can you ship faster?

Air freight and express vessels exist but are rarely sensible for machinery. The realistic lever is starting earlier, not paying for speed.

What documents arrive with the machine?

Commercial invoice, packing list, bill of lading, certificate of origin, and test or conformity certificates where your country requires them. The inspection report and packing photographs are sent before the balance is due.